30 days to target completion date


The new entrance takes shape


The upstairs rear rooms are all plastered. Plastering is advancing downstairs with the floor being laid next week. The main chapel is ready to be plastered.

The balcony benches are being constructed and the  balustrades are about to be installed.

Viewed from the entrance to the balcony, from what used to be the organ loft, one can appreciate how all will look when complete – larger, lighter and much more flexible.

The manufacture of the windows – particularly the large complex windows that will be installed in the rear hall - has been held up so some delay is inevitable, but it is remarkable how well the build has kept to schedule. In a couple of months we will be worshipping God in the chapel again as so many generations have done before us.