Work is progressing very well with:
- Core steelwork at the rear complete
- Brickwork at both sides progressing well
- New internal door openings cut out
- Internal blockwork begun
- Gas, electric and water all in and ready for connection by service providers
Over the next two weeks:
- The first floor joists will be completed
- Work on roof timbers continues
- There will be 2 or 3 lorry deliveries a day
We continue to be very grateful to our neighbours for their
continued patience, and look forward to being able to thank them personally at
a party to celebrate later in the year.