Friday, 30 August 2013

Building site news

As we approach the end of the summer holidays work has continued unabated on the building site. 




What's been happening?

  • Concreting oversite work is complete
  • Brickwork is removed on the concourse
  • Work is 50% complete on felting and battening the low roof
  • The main roof is felted and battened
 
  • Scaffolding at the rear is complete
  • The old flooring in the Chapel has been removed
  • Installation of new timbers and insulation to the floor is now complete in the Chapel



In the next two weeks:

  • Low level roofs will be completed
  • Flat roofs will be covered
  • Underfloor heating and new floor in the Chapel will be finished
  • Brickwork will be completed
  • Roof tiling will begin

    Only a few more months to go..............