Things are still moving on according
to schedule and already:
- the rear brickwork is almost complete
- first floor joists are complete
- floor decking is laid
- roof construction is continuing
- balcony steelwork is complete
- rear scaffolding is complete
- all drainage work is complete
- most service trenches dug
During the first two weeks of
August work continues of the main roof and begin on the flat roof, and the
concreting of floors will begin.
We are thankful for the good weather which has allowed this work to continue on time.